Project Management Services

 

FACILITIES DIVISION
 

 

 


CONTRACT AWARD CHECKLIST – NTP CHECKLIST



The following items are provided by the Contractor through the Architect after issuance of LOI.  The Architect verifies accuracy of each and submits the complete package.

 

 

·        Contracts Agreement for Construction (ABC Form C-5)

·        Bonds for Performance and Materials (ABC Form C-6 & C-7)

·        Insurance, Including Builder’s Risk

·        Sale Tax Agreement

·        Superintendent’s Resume

·        List of Sub-Contractors (w/Letter of Recommendation by Architect)

·        Application for Payment Form (Cost Breakdown)

·        Construction Schedule

·        Disclosure Form

·        BCIA – 45-day Report

 


Click Here for Word Version of Document


Last revision: February 19, 2009 11:47 a.m.
Webmaster
UAB
Facilities Division
801 6th Ave. South
Birmingham, AL 35294
Copyright © 2004
UAB Privacy Statement